Tuesday, March 3, 2015

March Construction Update

ACWD pipeline replacement work is underway near the homes on Curtner Road off of Mission Blvd. in Warm Springs. This pipeline replacement work is to ensure that homes in the area have a reliable water supply following an earthquake.

To conduct this pipeline replacement work, the contractor requires a two-week road closure of Curtner Road between Mission Blvd and Briar Place beginning this week until mid-March. Over the next two weeks, construction crews will be installing a brand new ACWD water delivery pipeline that will connect to the newly installed SFPUC BDPL3&4 pipelines.

Residents in the area should take Paseo Padre Parkway for entry to and exit from the neighborhood during work hours.

City of Fremont Approved Work Hours / Road Closure Hours:
  •  Monday to Friday: 7 a.m. to 5 p.m.
  • Some Saturday work is permitted and may be required
  • 24/7 Road Closure of Curtner Road may be required for the safety of pedestrians and motorists.

Restoration Work Continues:
While construction continues on the ACWD water delivery pipelines, restoration work continues on the SFPUC Right-Of-Way where the new BDPL3&4 pipelines were installed last year.


Final completion of this project is anticipated for May 2015.