Construction Update: Sections of Sound Fencing to Come Down

Due to rainy conditions, the removal of fencing has been postponed. Fencing will be removed in mid-February.


Because the open trench work for both pipelines in the Right of Way has been completed, the contractor will begin removing sound fencing between Nugget Way and Mission Blvd.

Some fencing close to Mission Blvd. will remain until the completion of the project. This flexible sound fencing has significantly reduced noise and dust out of the neighborhood, and will continue to do so for ongoing work areas.

The sound fencing marked with blue lines will be removed.
 Fencing south of the blue lines, as well as north of Nugget 
Way, will remain.