Friday, March 29, 2013

Upcoming Saturday Work Planned Around Mission Blvd. in Fremont

On Saturdays March 30, April 6 and April 13, positioning of guide beams will take place between 9 a.m. and 7 p.m.

Workers using a crane will move a guide beam to install a temporary on-ramp bridge. When completely installed, this bridge will ensure uninterrupted access to the I-680.

We ask that you reduce speed while driving past the active construction site on Mission Blvd. and obey our safety signs while walking around the work areas. The northern sidewalk along Mission Blvd. is closed, and heavy machinery and excavated pits make it dangerous for joggers and pedestrians. Pedestrians should cross and use the south side of Mission Blvd.

Work will take place on the highlighted length of Mission Blvd., 
and parallel to the highlighted on-ramp.

The contractor will employ best management practices to control noise, dust and other disturbances around the site.

If you have questions or concerns, please call our 24-hour answering service at 866-973-1476.  



Tuesday, March 26, 2013

Project Update: Additional Sound Fencing Installed on Tissiack Way

As construction continues in Fremont, homeowners along Tissiack Place may have noticed the installation of additional sound fencing along the perimeter of the work area. The taller fencing was installed to ensure that noise disturbances to the residents are softened and dust does not escape our construction area.

These polymer sound walls will remain up for the duration of the project and have proven to be effective in reducing construction-related noise on past construction projects.

Learn more about the polymer sound walls.

Keeping Businesses Informed

Last week, the SFPUC communications team spoke with business owners and delivered information packets by hand to keep nearby businesses informed about upcoming construction activities that may affect deliveries due to the project’s on-ramp closures.

The Mission Blvd. corridor is home to a vibrant range of businesses including retail stores, office parks and restaurants.  If you are an employee of a business in the vicinity of the Mission Boulevard and I-680 interchange or live in the Warm Springs neighborhood, register your email in the right-hand column to receive timely traffic-related updates.

Tuesday, March 19, 2013

Project Update: Night Work Required to Complete Temporary Water Pipeline

Upcoming Night-time Work

Closure of an I-680 on-ramp and five hours of night work are necessary on Monday, March 25 beginning just after midnight and continuing until 5 a.m., as crews complete a pipe tie-in that will allow continuous water supply to customers while we upgrade this major water distribution line.

Last month, a water quality testing apparatus was installed to ensure the delivery of high-quality drinking water to Fremont residents and others. As a next step, the contractor will remove the testing apparatus and install another length of pipe.

This five-hour timeframe has been identified to ensure that work is completed prior to morning commute times.

What to Expect?

This night work will involve some excavation around the on-ramp area. In addition, crews will also use a crane to remove the testing apparatus from the ground and to lay the new pipe. Water service will not be interrupted during this process.

The contractor will employ best management practices to control noise, dust and other disturbances around the site. 

If you have questions or concerns, please call our 24-hour answering service at 866-973-1476

Why Night Time Work?

The regional water delivery pipelines in need of replacement are located directly under the I-680 freeway and the on/off-ramps of Mission Blvd. In order to access the pipeline, a phased traffic handling plan will be in place. This overnight on-ramp closure is one of a handful of traffic diversions that this project will require along this busy traffic corridor.
  The SFPUC, Caltrans and other governmental agencies have been working with the contractor on this phased traffic approach plan.

Tuesday, March 12, 2013

Nesting Season Arrives & Construction Continues while Keeping Birds Safe


Spring is here, and with it comes the primary nesting season for California’s birds. The SFPUC WSIP environmental team is taking precautions to discourage native species from setting up camp in trees where they may be disturbed by passing trucks and drilling activities.

To ensure the protection of the bird species, WSIP biologists Elizabeth Gruenstein (pictured to the right) and Jill Grant are hanging shiny nesting deterrents in trees around the BDPL3&4 jobsite in Fremont. Owl shapes, “eyes” and reflective ribbon will scare away birds that come to nest near construction. In years to come, birds will return to the same trees to nest.  

White tailed kite and red-tailed hawk are among the species 
that biologists hope to keep away from construction.

The SFPUC communications team has spoken with a number of residents around the jobsite who have approved the placement of deterrents within their properties. If you have any questions about an unexpected object hung on one of your tree limbs, don’t hesitate to call our 24-hour answering service at (566) 973-1476. Thanks for helping us protect our wildlife!

Balloon deterrents have large “eyes” which scare birds 
that would otherwise nest too close to construction.


Friday, March 8, 2013

Project Update: Sidewalk Installed on South Side of Mission Blvd. at I-680 in Fremont


As construction continues along Mission Blvd., we ask pedestrians to obey our construction and safety signs regarding sidewalk closures. 

Currently, the contractor has installed a new sidewalk along the south side of Mission Blvd., north of the I-680. Residents are asked to use this sidewalk instead of crossing to the north side of the road, which is currently under construction. For your safety, please do not cross Mission Blvd. between I-680 and Curtner Road. 

Sidewalk Closure: On Mission Blvd. near Paseo Padre Parkway
Pedestrians must use the sidewalks marked in blue above. 
Sidewalks marked in red are currently closed.
  
While You Were Sleeping, We Were Working 
To date, the contractor has completed six nights of critical work including accessing and re-routing existing pipes below an on-ramp to I-680.

Play our short video to see photos of the action:



Saturday, February 23, 2013

Late Night On-Ramp Work Required to Install Temporary Water Pipelines

Night closures of an I-680 on-ramp are required throughout the week of Feb. 25, as crews work to install temporary water pipelines in preparation for the replacement of the Bay Division Pipelines Nos. 3 & 4 (BDPL3&4) regional water delivery pipelines later this spring.The temporary water pipelines will ensure that nearby neighbors continue to have a water supply throughout  construction.
 
During the week of Feb. 25, five-hour on-ramp closures will begin just after midnight and reopen at 5 a.m. in time for the morning commute.
  • Tuesday morning, 12:01 a.m. - 5:00 a.m.
  • Wednesday morning, 12:01 a.m. - 5:00 a.m.
  • Thursday morning, 12:01 a.m. - 5:00 a.m.
  • Friday morning, 12:01 a.m. - 5:00 a.m.
What to Expect
This night time work will involve some excavation work around the on-ramp area. The contractor will employ best management practices to control noise, dust and other disturbances around the site.

Why Night Time Work?
The regional water delivery pipeline in need of replacement is located directly under the I-680 freeway and the on/off-ramps of Mission Blvd. In order to access the pipeline, a phased traffic handling plan will be in place.

These overnight on-ramp closures are one of a handful of traffic diversions that this project will require along this busy traffic corridor. 

The SFPUC, Caltrans and other governmental agencies have been working with the contractor on this phased traffic approach plan.

Detour Information 
To detour during this five-hour on-ramp closure, use Warm Springs Blvd. (North), and make a right at Auto Mall Parkway to merge onto the I-680 North.

Trucks should take the Warm Springs Blvd. detour or turn left at Durham Rd. to access I-680 before the Mill Creek bridge.

Questions 
24-Hour Answering Service: (866) 973-1476 
Email: djaimes@sfwater.org    
Project Overview: www.sfwater.org/wsip/SeismicUpgrade   



Thursday, February 14, 2013

Late Night Work Required to Install Temporary Traffic Bridge at I-680 and Mission Blvd. Prior to Pipeline Construction

Due to wet weather conditions, the Wednesday, Feb. 20 on-ramp work has been postponed. The on-ramp will be closed at midnight for five hours, and reopen on Friday, Feb. 22 at 5 a.m. in time for the morning commute.

Upcoming Construction Activities
Beginning midnight on Friday, Feb. 22, an I-680 on-ramp closure is scheduled, as crews need to redirect traffic along this traffic corridor in order to access the water pipeline later this spring. 

This closure is necessary for work on a water pipe below the on-ramp. The on-ramp will be closed for five hours, and will reopen on Friday, Feb. 22 at 5 a.m. in time for the morning commute. This time frame has been identified to ensure that work is completed prior to morning commute times. Two additional late night on-ramp closures are required in the coming months to complete this work.

What to Expect?
This night time work will involve some excavation work around the on-ramp area. 
The contractor will employ best management practices to control noise, dust and other disturbances around the site.

Why Night Time Work?
The regional water delivery pipeline in need of replacement is located directly under the I-680 freeway and the on/off-ramps of Mission Blvd. In order to access the pipeline, a phased traffic handling plan will be in place. These overnight on-ramp closures are one of a handful of traffic diversions that this project will require along this busy traffic corridor.
The SFPUC, Caltrans and other governmental agencies have been working with the contractor on this phased traffic approach plan.

Traffic Detour Information
To detour during this five-hour on-ramp closure, use Warm Springs Blvd. (North), and make a right at Auto Mall Parkway to merge onto the I-680 North.



This closure is necessary to complete the temporary bridge installation to ensure that motorists will be able to use this major traffic commute artery at all times. During the environmental review period, this option was identified as being the least disruptive alternative.