On Saturday, November 23 and Sunday, November 24, construction work will take place in the SFPUC right of way near the Mission Blvd. to I-680 on-ramp between 9 a.m. and 6 p.m.
Workers will be excavating and removing elements of the original water system to ensure that construction can resume on-schedule next week.
Construction activities will continue next week, Monday, November 25 through Wednesday, November 27, and will be on hold Thursday, November 28 and Friday, November 29 for the Thanksgiving holiday.
The project team wishes you a safe and happy holiday.
If you have questions or concerns, please call our 24-hour answering service at 866-973-1476.
Para informaciĆ³n en espaƱol, por favor llame 866-973-1476