The water pipeline project at Mission Blvd. and I-680 is one of three major construction projects laying the foundations for Fremont's new "Innovation District."

We encourage residents and business owners to join the City of Fremont, VTA, BART, CalTrans and SFPUC on Thursday evening to learn about the lifelong benefits and short term inconveniences that are associated with our projects.

Traffic-related detours and temporary lane/road/on-ramp closures will affect the widely used I-680, I-880 and Mission Blvd. commuter arteries over the next year. At the meeting you can learn more and ask questions about all three projects.



  1. The Seismic Upgrade of Bay Division Pipeline Nos. 3&4 at Hayward Fault 
    The major upgrade of two regional water delivery pipelines that cross the Hayward Fault involves ongoing work activities through the end of 2014.
  2. VTA Mission/Warren Area Improvements Project
    A 12-month Warren Avenue road closure between Kato Road and Mission Falls Court is scheduled to begin Monday, June 17, 2013. The closure will allow construction crews to trench Warren Avenue under the future BART system and build bridges for both BART and the Union Pacific Railroad.
  3. BART Warm Springs Extension Project
    Work will include lane closures on South Grimmer Boulevard between Warm Springs Boulevard and Lopes Court to accommodate BART track way overpass.