Tuesday, November 6, 2012

In case you missed our open house...

On behalf of the entire SFPUC construction management team, we would like to thank you for attending our recent open house event to learn more about the Seismic Upgrade of Bay Division Pipeline Nos. 3 and 4 (BDPL3&4) Project in Fremont. It was a pleasure to meet all of you and we enjoyed discussing the project and answering your questions about this upcoming work. Local residents, businesses, government agencies and even a high school science class attended our open house. We hope you all gained more knowledge about this project and the overall Hetch Hetchy Water System Improvement Program!

To better visualize the seismic improvements that will be made to the regional water delivery pipeline, please view our short video on the engineering that will be undertaken to construct this pipeline along the Hayward Fault. Click on the video icon at the end of this email.



Nearly 20 local residents attended the open house to learn more about this important regional project!

Ms. Lisa Ishimine and her science class at Mission San Jose High School in Fremont attended the open house. Approximately 25 students earned extra credit for attending. The idea behind their participation was to allow Ms. Ishimine's students to become engaged in a public works project in their community and to learn about how their water system works.

View our video on the seismic upgrade improvements to the BDPL Nos. 3 & 4 project at Hayward Fault:
 

Monday, October 22, 2012

Learn about upcoming construction in your neighborhood!

Before construction begins in mid-November, please join us on Thursday, Nov. 1 to learn more about the Seismic Upgrade of Bay Division Pipeline Nos. 3 and 4 (BDPL3&4) Project in Fremont. The project team will be on hand to discuss the benefits and potential impacts of this pipeline upgrade work. Come by anytime between 3 and 4:30 p.m. to ask questions, review informational materials and to find out more about this important project! For more details, go to www.sfwater.org/seismicupgrade.

Event Details
What: Learn about the upcoming BDPL3&4 Seismic Upgrade Project
When: Thursday, Nov.1, 2012
Time: 3 to 4:30 p.m.
Where: Intersection of Tissiack Way & Nugget Place in Fremont
Light refreshments will be served.


For more information, please call 415.551.4675 or RSVP by emailing djaimes@sfwater.org.



Event Map

Tuesday, October 9, 2012

Be Prepared!


The 23rd anniversary of the freeway-flattening Loma Prieta earthquake is coming up on October 17th. In the event of a similar emergency, will you be prepared? Will you have enough drinking water?

Make This October Emergency Preparedness Month!
The San Francisco Public Utilities Commission (SFPUC) operates the Hetch Hetchy Regional Water System, which provides high-quality drinking water to 2.6 million residents and businesses across four Bay Area counties. The SFPUC is making the investment to seismically upgrade regional water facilities, tunnels, and pipelines. However, it is important for you to remember that smaller pipelines leading to your home might be damaged in an earthquake. As a result, water from your tap may be unavailable for up to 72 hours or longer.

To prepare for an emergency:

Keep a 3-day water supply just in case!
• Each family member needs 1 gallon per day
• Store tap water in food-grade plastic containers; replace every 6 months
• Store bottled water in the original sealed containers; replace according to expiration date.

If your supply runs out, you can treat your water!
• Boil it for 3 minutes, or disinfect it by adding regular household bleach
• Add 8 drops of bleach per gallon of water
• Shake or stir then let it stand for 30 minutes




For more tips, view our emergency preparedness videos and website: http://www.sfwater.org/beprepared or follow @WSIPInTheNews.

Tuesday, October 2, 2012


Pipeline Construction Work Coming to Fremont

This fall, crews will begin work on the seismic upgrade of two water pipelines where they cross the Hayward Earthquake Fault in Fremont. The pipelines, known as Bay Division Pipeline (BDPL) Nos. 3 and 4, cross three traces of the fault near the intersection of Mission Boulevard and I-680. The goal of the project is to make sure that all of our Bay Area customers have reliable water delivery following a major earthquake.


Preparation work and pipeline work will begin near Crawford Street and Tissiack Way, including the installation of fencing and staging equipment.Environmental monitoring activity will take place along the SFPUC Right of Way and around the work area.


Before major construction activities begin this November, crews will perform environmental surveys of the project site. Also, modifications will be made to nearby electrical, sewer and water lines to avoid utility interruption during construction.
Overall construction is anticipated to be complete in summer 2014.

For more information, contact our 24-hour answering service at 866-973-1476 or e-mail djaimes@sfwater.org.


More updates to our construction activity will be distributed as the work nears.

Project Map 
 

Wednesday, June 6, 2012

USD Night Work

Union Sanitary district will be continuing their night work on Mission Blvd. USD contractor encountered a new ground conditions and will require a different technique to complete work. Neighbors may experience an increase in construction noise while construction progresses past this section. It is estimated to move through this area in a single nights work. The project will monitor noise and other environmental impacts to ensure they are within permitted limits. Traffic controls will be in place as necessary. If you have any questions please call USD Project Liaison, Conor McNamara, at (415) 200-5229.

Friday, June 1, 2012


Look How Far the Water System Improvement Program Has Come

The Water System Improvement Program (WSIP) is $4.6-billion of infrastructure upgrades, including more than 80 projects located in six Bay Area counties to ensure the highest quality drinking water and a reliable water supply to customers following an earthquake. These seismic improvements include dams, tunnels, pipelines, treatment plants and many more facilities that serve 2.6 million Bay Area customers. 2011 marked the start of the WSIP’s most active construction year to date. As of March 31, 2012, 55 out of 81 local and regional projects have been completed. All WSIP projects are forecasted to be complete in 2016. To view our progress and learn more about our water system, check out our video of water system improvements in your area here: http://www.youtube.com/watch?v=5qwqUcPIOyM&feature=youtu.be 

 

Friday, May 11, 2012

Nesting Birds & Night Work | Union Sanitary District Project



We are excited to share that USD’s Contractor, K.J. Woods Construction Company Inc., began work on the sewer relocation. Crews set up the trailers and construction areas so they can get their work done as efficiently as possible over the next several months.

USD’s construction management firm is the Covello Group. Their trailer is onsite to work closely with the USD Contractor addressing issues in the field immediately. Neighbors are encouraged to contact Project Liaison, Conor McNamara, at (415) 200-5229 or stop by the trailer to learn about their relocation project.

Covello Group Construction Management Trailer

Nesting Birds - It is spring and the Killdeer and Bushtit birds are nesting near one of the tunneling sites at Mary Beth Court, Fremont. The Contractor will begin work in another location as to not disturb the nesting birds.


Killdeer Bird

Bushtit Bird

Night work on Mission Boulevard will be May 14-18 & May 21-25 - To minimize the traffic impacts, night work will occur along Mission Blvd. near the I-680 NB on-ramp. There will be a lane closure on westbound Mission Blvd. and a closure of the NB I-680 off-ramp to westbound Mission Blvd. See the project map below for the work area.

Additional Notices were sent by the Contractor to adjacent neighbors who may be impacted by this work.

The Union Sanitary District (USD) sanitary sewer line relocation work is to prepare the site for the upcoming seismic upgrade of Bay Division Pipeline Nos. 3 and 4.